A public hearing lasting around four hours and marked by several tense moments was held at the Kölcsey Centre in Debrecen on Monday over the environmental permit of EcoPro’s Debrecen plant. Around 150 people attended the forum organised by the Hajdú-Bihar County Government Office, with questions extending far beyond the narrow scope of the permit modification. Residents raised concerns ranging from noise pollution and water quality to official inspections and the wider battery industry developments in Debrecen.
Officially, the hearing concerned an amendment to EcoPro’s existing environmental permit. The South Korean company’s first European plant produces high-nickel cathode materials used in lithium-ion batteries, and the new procedure is required to introduce the production of a new type of cathode material.
At the beginning of the hearing, representatives of the authority and the company presented the permitting process and the planned changes. According to the environmental assessments presented, the level of air pollution remained below the health limit in all cases examined, while the air-quality impact area does not extend to inhabited areas.
The noise assessment, however, prompted stronger reactions. According to the expert, the noise protection impact area will become larger as a result of the development, mainly towards the south, and will reach within a few metres of the administrative boundary of Mikepércs, although the calculations indicate that it will not affect inhabited areas.
“It is so loud around 2 a.m.”
Several shouts came from the audience in response. One participant said that around 2 a.m. the noise was so loud that residents could not sleep, and claimed that wastewater was also being discharged at night.
An EcoPro representative later acknowledged that there had indeed been a nighttime “blow-off” operation that caused significant noise. He said the company had already taken the necessary measures to reduce the problem.
The issue later came up again when Zoltán Tímár, the mayor of Mikepércs, asked the authority whether it had carried out its own control measurements during such events.
A representative of the government office said its laboratory was capable of conducting official noise-protection inspections, but no control measurement had been carried out in this case while the noisy blow-off was taking place. According to the authority, the blow-off operation lasted only a few days.
Mikepércs questions the adequacy of inspections
Zoltán Tímár also objected to what he said was the exclusion of Mikepércs from EcoPro’s environmental permitting procedure. According to the mayor, the circumstances surrounding the noise measurements were particularly unclear.
He asked when and under what conditions the measurements had been carried out, after a noise barrier previously erected at the site had subsequently been dismantled. He also complained that the town administration had not been informed when measurements were conducted in the administrative area of Mikepércs, meaning, in his view, that the municipality had no opportunity to monitor or verify them.
The mayor also questioned the air-quality assessment. He argued that the actual wind conditions in the area should be taken into account, since winds from the northeast could mean that emissions do not necessarily remain confined to the immediate vicinity of the industrial area.
Tímár also made it clear that Mikepércs does not want any more battery plants built in the vicinity of the settlement.
Combined impact of the factories also questioned
Another issue raised at the hearing was whether the authorities examine the combined, so-called cumulative environmental impact of industrial plants already operating or planned in Debrecen.
The mayor referred to combined water and energy consumption, emissions and noise pollution as examples.
The government office responded that there is no legal requirement to assess the entire environmental impact of every investment in one single cumulative study. However, the authority must examine whether the effects of the particular investment could add to the effects of other activities. According to the authority, emissions and noise from surrounding industrial facilities were taken into account in the air-quality and noise assessments.
The government office also said that it had previously issued EcoPro with a 31-point request for additional information, and that the procedure was still at the stage of clarifying the facts.
Water and sediment samples brought to the hearing
One of the most unusual moments of the hearing came when a speaker presented water and sediment samples. The woman said she was a chemist and had previously worked as a quality assurance manager, and that she had taken samples from the Kondoros with her own team and had them analysed in a laboratory at her own expense.
She claimed that the tests detected high levels of lithium, arsenic, cobalt and lead. She also said that there had still been water in the area when the samples were taken, but that the Kondoros had since dried up.
According to the speaker, substances accumulated in the dried sediment could later enter the air and be carried away by the wind. She also mentioned NMP among the substances identified in the results she presented and raised concerns about potential health risks associated with it.
Another water sample she presented was allegedly taken from a farm located near the battery plants. She said the property was approximately 600–700 metres from the factories and that the residents had to use a water purification system.
It is important to note, however, that the results of the privately commissioned water tests presented at the public hearing were claims made by the speaker; they were not presented as official findings of an environmental authority.
EcoPro says all stormwater tests have complied with limits
In response, an EcoPro representative said the company had carried out baseline tests in the stormwater reservoirs at the site before beginning operations.
According to the company, the tests showed that the stormwater complied with the prescribed discharge limits. Since then, accredited measurements have been carried out every three months on the stormwater network, and the company says all tests so far have complied with the applicable limits.
According to EcoPro, the company only discharges stormwater from the site after confirming that it meets the prescribed limits.
The company also said that nine monitoring wells are operating at the site and that they are continuously monitored.
Concerns went beyond the new technology
The new technology’s water consumption and waste generation were also discussed at the hearing. According to the plans presented, production of the new type of cathode material could require more water, while waste generation could increase by approximately three percent.
Several participants also alleged that environmental inspectors had previously not always been allowed to enter the EcoPro site. The plant has also previously been fined for violating requirements set out in its environmental permit.
According to those raising the concerns, the issue is therefore not only what new requirements will be imposed on the company, but also how compliance with those requirements will be monitored in practice.
Papp László and Tisza representatives also missed
The role of Debrecen’s city leadership and the question of political responsibility also came up repeatedly during the hearing.
Several participants criticised the absence of Debrecen’s Fidesz mayor, László Papp. Representatives of the Tisza Party from Debrecen were also missed by those attending.
István Apáti, a Member of Parliament from the Mi Hazánk party, did attend the hearing and recalled an earlier initiative by his party. He said that if a binding local referendum had been held earlier, “there would be no battery plant in Debrecen now.”
The mayor’s absence continued to generate debate after the hearing. According to László Papp’s Monday schedule, he visited the construction site of the Fekete István Street road project, where the third phase is currently underway on a 420-metre section between Makszin Mihály Street and Bocz Ernő Street.
Whistling and booing marked the end of the lengthy hearing
The atmosphere became increasingly tense during the several-hour event. Dissatisfaction was particularly evident when attendees expected answers to questions that the authority said fell outside the direct scope of the permit amendment.
Whistling and booing could be heard in the room several times. Some participants described the hearing as a parody or farce, while others complained that they had not received immediate answers to the questions they considered most important.
The government office eventually said that the comments made at the hearing would be taken into account during the permitting procedure. Questions concerning other issues can be submitted to the authority in writing and will also receive a response.
According to the authority, the full audio recording of the public hearing will be published on its website within 15 days.