No trams until the end of the month

Local News

According to the plans, by November 20 the days of tram-substitutional buses would have been over. But surprisingly, unexpected problems have occured during the construction works, so from November 18 trams will not run at all.

Surprise for the workers of the construction: some public utility cables and pipes are not exactly there where they should be according to the registers. Such problems, supplemented by other technical difficulties during the construction bring extra work and some delay in the whole process, of course.
So between 18 and 30 November, tram-substituting buses will run all over No. 1 tram line.
Good in the bad, passengers do not have to run any more between the bus and the tram at Debrecen Plaza.