New Paks Power Plant Blocks Could Start Commercial Operation in 2029

National

Two new blocks at Paks could start commercial operation in 2029 and in 2030, the minister in charge of the expansion of Hungary’s sole commercial nuclear power plant said at a meeting of the Tolna County Council on Friday.

János Süli said the two blocks would have a six- to eight-month test run before starting commercial operation. He noted that an application for the implementation licence for the two blocks had been submitted to the National Atomic Energy Office (OAH) by project company Paks II on June 30, 2020. The office has twelve months to review the application with an option for a three-month extension, which means the licence should be issued by the end of September 2021, he added.

The state of Russia is financing 80% of the 12.5 billion euro cost of the blocks. The general contractor for the upgrade is Russia’s Rosatom.

The Paks plant’s existing four blocks, each with a nominal capacity of 500MW, account for about half of domestic electricity generation.

 

hungarymatters.hu

Iris Properties

- 3 rooms flat close to Uni

80 m2 flat for rent
350 000 Ft

- Renewed flat close to Interspar

50 m2 flat for rent
280 000 Ft

- Rowhouse for rent close to IT Services

107 m2 flat for rent
500 000 Ft

- 3 rooms flat close to Engineering Faculty

71 m2 flat for rent
300 000 Ft

office for rent

- Nice flat close to Plaza

37 m2 flat for rent
220 000 Ft

Leave a Reply

Your email address will not be published. Required fields are marked *